The Gateway Projects Tracker

The public record of named higher-risk building projects moving through the Building Safety Act gateways: who has been approved at Gateway 2, who is still in the process, how long decisions actually took, and, as the first movers reach it, who has been handed over through Gateway 3. Compiled from trade press reporting and verified before publication.

9

named GW2 approvals tracked

26

average weeks to decision (where published)

1

applications in process

Gateway 2: approved projects

Named schemes with building control approval from the BSR, newest reporting first. Decision times range from 13 weeks to 42 weeks across this set; the spread is the story.

ProjectLocationDeveloper / ContractorScaleStatusDecisionWeeks

Upper Brook Street PBSA

No conditions; roughly 1,500 design documents signed off.

ManchesterMcLaren Property (with Kadans) / McLaren Construction23 storeys, 737 bedsApproved2025-0927

Brewery Gardens

The pre-reform benchmark: 42 weeks to a decision.

ManchesterLatimer (Clarion Housing Group)Residential HRBApproved202542

Medlock Street

HG Construction's first Gateway 2 approval, called a turning point.

ManchesterHG ConstructionPBSAApproved2025-05-

Roc Club, Rockingham Street

21 weeks to approval.

Elephant and Castle, LondonCKC Properties / Valpre Capital / HG ConstructionStudent towerApproved2025-Q421

East London co-living scheme

13 weeks, close to the statutory clock.

LondonHG ConstructionCo-livingApproved2025-1113

Kingsland Road

Hailed as a record-time approval and a breakthrough moment.

Hackney, LondonMorro (Meanwhile Group) / HG ConstructionCo-livingApproved2025-12-

Vivere Residences, Cornbrook

64.2m pounds Maslow funding; second staircase added to the hotel element during the process; start on site July 2026.

ManchesterForshaw Land and Property / Domis24 storeys, 237 flats + 88-key aparthotelApproved2026-06-

Haymarket

Bristol's tallest; 29 and 18 storey towers; processed through the Innovation Unit.

BristolOlympian Homes (with Cain) / RG Group29 storeys, 442 student beds + 150 co-livingApproved2026-02-

Smithfield Plot 1, Digbeth

A regional signal beyond London and Manchester.

BirminghamProsperityUp to 305 apartmentsApproved2025-10-

Gateway 2: in the process

Publicly reported applications awaiting a decision.

ProjectLocationDeveloper / ContractorScaleStatusDecisionWeeks

Piccadilly East tower

Submitted March 2026; 91-week build target; JRL pipeline includes Luton BTR and two Woking schemes.

ManchesterJRL Group / Midgard28 storeys, 359 flatsSubmitted--

Gateway 3: handed over

By early September 2025 the BSR had received only 16 new-build Gateway 3 applications and issued 9 completion certificates, and almost none of those schemes have been named publicly. As the 2025-26 approval wave completes on site through 2026-27, the first named handovers will be tracked here. If you have one to report, tell us.

How this tracker works

Rows are compiled from named reporting in the construction trade press, including Construction Enquirer, Building, Place North West and Green Street News, and from developer and contractor announcements. The BSR publishes aggregate decision statistics but does not name projects, so a public list only exists where the industry reports it. Every row carries the publication it came from and the date we verified it. Blank cells mean the detail was not published, not that it does not exist. See the live aggregate numbers on the Gateway 2 timescales page, and what the completion stage demands on the Gateway 3 hub.

Data verified 14 July 2026 against the publications listed per row. Corrections welcome via the contact page. This page is information, not legal advice.